Filters
Question type

Study Flashcards

Which of the following is true of the historical simulation method for calculating VaR?


A) It fits historical data on the behavior of variables to a normal distribution
B) It fits historical data on the behavior of variables to a lognormal distribution
C) It assumes that what will happen in the future is a random sample from what has happened in the past
D) It uses Monte Carlo simulation to create random future scenarios

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

What is the method of testing how often a VaR with a certain confidence level was exceeded in the past called?


A) Stress testing
B) Back testing
C) EWMA
D) The model-building approach

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Which of the following is true of a covariance matrix?


A) The numbers on the diagonal are variances
B) The numbers on the diagonal are standard deviations
C) The numbers on the diagonal are all one.
D) The numbers on the diagonal are all zero

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

In the case of interest rate movements the most important factor corresponds to


A) A parallel shift
B) A slope change
C) A bowing
D) An increase in short rates

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

Which of the following is true?


A) Cash flow mapping is a way of calculating the present value of cash flows
B) Cash flow mapping is used to handle interest rate exposures in the model building approach
C) Cash flow mapping is used to handle interest rate exposures in the historical simulation approach
D) None of the above

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

Which of the following is true?


A) The quadratic model approximates daily changes using delta and gamma
B) The quadratic model approximates daily changes using delta, but not gamma
C) The quadratic model approximates daily changes using gamma, but not delta
D) None of the above

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

The gain from a project is equally likely to have any value between −$0.15 million and +$0.85 million.What is the 99% expected shortfall?


A) $0.145 million
B) $0.14 million
C) $0.13 million
D) $0.10 million

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

The 10-day VaR is often assumed to be which of the following


A) The 1-day VaR multiplied by 10
B) The 1-day VaR multiplied by the square root of10
C) The 1-day VaR divided by 10
D) The 1-day VaR divided by the square root of 10

E) A) and C)
F) All of the above

Correct Answer

verifed

verified

A position in options on a particular stock has a delta of zero and a gamma of 4.The stock price is 10.Which of the following is the approximate relation between the change in the portfolio value in one day,dP,and the return on the stock,dx


A) dP = 4 times the square of dx
B) dP = 2 times the square of dx
C) dP = 20 times the square of dx
D) dP = 200 times the square of dx

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

Which was the minimum capital requirement for market risk in the 1996 BIS Amendment?


A) At least 3 times the 10-day VaR with a 99% confidence level
B) At least 3 times 7-day VaR with a 97% confidence level
C) At least 2 times 5-day VaR with a 95% confidence level
D) 1-day VaR with a 99% confidence level

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Which of the following is true of the 99.9% value at risk?


A) There is 1 chance in 10 that the loss will be greater than the value of risk
B) There is 1 chance in 100 that the loss will be greater than the value of risk
C) There is 1 chance in 1000 that the loss will be greater than the value of risk
D) None of the above

E) None of the above
F) All of the above

Correct Answer

verifed

verified

In a principal components analysis which of the following is the quantity of a particular factor in an observation


A) Factor loading
B) Factor score
C) Factor size
D) Factor rating

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

In the case of interest rate movements the second most important factor corresponds to


A) A parallel shift
B) A slope change
C) A bowing
D) An increase in short rates

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

Consider a position in options on a particular stock.The position has a delta of 12 and the stock price is 10.Which of the following is the approximate relation between the change in the portfolio value in one day,dP,and the return on the stock during the day,dx


A) dP=12dx
B) dP=1.2dx
C) dP=120dx
D) dP=22dx

E) A) and C)
F) B) and D)

Correct Answer

verifed

verified

Which of the following is true when delta,but not gamma,is used in calculating VaR for option positions?


A) VaR for a long call is too low and VaR for a long put is too low
B) VaR for a long call is too low and VaR for a long put is too high
C) VaR for a long call is too high and VaR for a long put is too low
D) VaR for a long call is too high and VaR for a long put is too high

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

Which of the following is true


A) Expected shortfall is always less than VaR
B) Expected shortfall is always greater than VaR
C) Expected shortfall is sometimes greater than VaR and sometimes less than VaR
D) Expected shortfall is a measure of liquidity risk wheras VaR is a measure of market risk

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

A German bank has exposure to the S&P500.Which of the following is true


A) The S&P 500 index should be always be measured in U.S. dollars when VaR is calculated
B) The S&P 500 index should be always be measured in euros when VaR is calculated
C) Either A or B can be done
D) The S&P 500 index should be measured in euros only if the bank has not got a U.S. subsidiary.

E) None of the above
F) C) and D)

Correct Answer

verifed

verified

B

An investor has $2,000 invested in stock A and $5,000 in stock B. The daily volatilities of A and B are 1.5% and 1% respectively and the coefficient of correlation is 0.8. What is the one day 99% VaR? Assume that returns are multivariate normal (Note that N(-2.326) =0.01)


A) $177
B) $135
C) $215
D) $331

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

The gain from a project is equally likely to have any value between -$0.15 million and +$0.85 million.What is the 99% value at risk?


A) $0.145 million
B) $0.14 million
C) $0.13 million
D) $0.10 million

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

B

Which of the following describes stressed VaR?


A) It is based on movements in market variables in stressed market conditions
B) It is VaR with a very high confidence level
C) It is VaR multiplied by a factor of 3
D) None of the above

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

A

Showing 1 - 20 of 20

Related Exams

Show Answer